Air Changes Confusion by Bryan Orr

Air changes per hour (ACH/ACPH) simply describes how many times the quantity of air in a room (or structure) is completely replaced per hour.

If you have a 10’x10’x10′ room, the room contains 1000 cubic feet of air. If the supply and return to the room is supplying a balanced 100 CFM (cubic feet per minute) of air to the room, you would have 100 CFM x 60 minutes = 6,000 CFH (cubic feet per hour), which would equal 6 air changes per hour (6,000/1000 = 6).

Different spaces have different ventilation requirements based on occupancy level (how many people are in the room) and use type. This is a fairly simple thing to calculate based on the cubic feet of air in a room. This is NOT the heat gain/loss of the space; it is only the ventilation rate of the space. Generally, ACH is used as a guideline or reference for design and not as a basis for the design; it’s more of a solid rule of thumb used to check a ventilation design against the real world.

This ventilation rate shouldn’t be confused with the outdoor air requirements, which is a different but related consideration and is based on ASHRAE 62.1 and 62.2.

In some cases, when discussing ventilation for an entire structure, ACH will be used to describe “tightness” and is referenced in many codes as a standard for the structure. For example, when performing a blower door test, a building test professional will use an air changes number to demonstrate whether a home or building is built to a tightness standard and how much supplemental outdoor air needs to be added to the space per hour.

Even more specifically, a standard called ACH50 is used with a blower door to calculate the leak rate of a structure when the space is pulled into negative 50 pascals of pressure by the blower door and the leak rate calculated.

In most cases, a room/zone will be sized for airflow according to the heat gain/loss to include outdoor air requirements. Then, the ventilation requirements will dictate the need for additional mechanical ventilation or fan-on position to provide the required air changes per hour.

In short, don’t simply provide a room with system airflow that is consistent with the air change per hour rule of thumb and assume it will be properly conditioned and balanced. As with most things, it isn’t that simple.

—Bryan

Co-Founder and President at Kalos Services, Bryan Orr has been involved in HVAC training for over 13 years. Bryan started HVAC School to be free training HVAC/R across many mediums, For Techs, By Techs.

Contact Bryan by emailing bryan@HVACRSchool.com.

Visit https://hvacrschool.com – The place to learn some things you’ve forgotten along the way as well as remind you of some things you forgot to know in the first place.

 

 

 

 

 

In the Spotlight

MAN Energy Solutions to Supply World’s Largest Air-to-Water Heat Pump for Helsinki’s District Heating

Finland’s capital city to reduce CO2 emissions by 26,000 tons annually with MAN heat pump technology Mega heat pump to harness ambient air and renewable electricity for heat generation MAN Energy Solutions to deliver a 33 MW air-to-water heat pump unit – the world’s largest ever used for a district-heating plant  Finnish energy company Helen Oy has commissioned MAN Energy

Read More »

FEATURES

Informing & Supporting
Conditioning Air Professionals
& the Industry